Balfour Beatty Ground Engineering, one of the UK’s leading specialist geotechnical contractors, is making significant progress with piling works at Marble Arch Place. The contract for Multiplex will provide foundations for Almacantar’s 18-storey residential tower and seven-storey commercial building overlooking Hyde Park in London.

With site preparation work now complete, Balfour Beatty Ground Engineering has just started to construct the 110 piles required, which are up to 43m in length. These act as structural columns to provide the towers' solid foundations.

Work on the 278 metre diaphragm wall, the underground structure designed to retain soil and support heavy loads from above, will begin shortly, leading to the creation of a new 22m deep basement.

The project is utilising the skills of 35 expert engineers, including three graduates and an apprentice.

Malcolm O’Sullivan, Managing Director for Balfour Beatty Ground Engineering, said:

"Marble Arch Place presents Balfour Beatty Ground Engineering with a technically challenging but exciting project. Among the challenges are historic foundations in the form of 39 piles from the 1960's building which previously stood on the site and must be removed. Five of these are 1.8m in diameter; some of the biggest in the UK. We're utilising the latest equipment and our expertise to ensure their removal and our subsequent works run smoothly."

Preparatory work at Marble Arch Place commenced in June 2017 with the ground engineering works due for completion in early 2018 and the project due to complete in 2020.

ENDS

Media enquiries to:
Aurelie Hulse
Balfour Beatty
+44 (0)207 963 2150
aurelie.hulse@balfourbeatty.com
www.balfourbeatty.com | follow us @balfourbeatty

All non-media related enquiries should be directed to +44 (0)20 7216 6800 or info@balfourbeatty.com

 

Notes to editors:

• Balfour Beatty Ground Engineering is one of the UK’s leading specialist geotechnical contractors providing innovative piling and ground improvement solutions across all sectors. The company’s comprehensive ground engineering capabilities, equipment and experience provide the solid foundations for buildings of any height, ranging from city skyscrapers to house foundation packages.


• Projects in Balfour Beatty Ground Engineering’s current portfolio in London include a £36m project to create the foundations for two towers reaching 42 and 58 storeys at One Nine Elms, a £28m contract to regenerate a region to the south of Battersea Power Station, providing the stable foundations for the area’s new homes and high street, and a £15m contract to deliver the foundations at Marble Arch Place.


• Past projects include the foundation works for The Shard, the UK's tallest building, the foundations for Heathrow's new Terminal 2 building and the foundations for the National Sports Arena's Velodrome, Office Hub and Sports Arena in Glasgow, which hosted the 2014 Commonwealth Games.